Illustrative image – not actual.
The Sandur Manganese & Iron Ores began commercial operations at 0.4. million tpa coke oven plant and ferro alloy furnaces with effect from 18 January 2021.
The bhoomi poojan and foundation stone laying ceremony took place on 19 March 2018 for Phase-I of one million tpa iron and steel project, entailing setting up 0.4 million tpa coke oven plant, waste heat recovery boilers and 0.4 million tpa pig iron blast furnace at Vysanakere, Hosapete in Karnataka.
The trials from batteries 1 & 2 of the coke oven plant commenced in January 2020, new 24 MVA Ferro Alloy furnace in February 2020, batteries 3 & 4 of coke oven plant from November 2020 and refurbished 20 MVA Ferro Alloy furnace from 18 January 2021.
The lenders’ engineers completed their visit to the plant on 19 January 2021 and are expected to issue a certificate to theBankers regarding completion of the project and declaration of the commercial operations with effect from 18 January 2021.
Performance Guarantee Tests will be taken up in due course of time.