Samruddhi Mahamarg Phase-1 opening delayedIllustrative image – not actual.
The Maharashtra government’s Hindu Hurudaysamrat Balasaheb Thackeray Maharashtra Samruddhi Mahamarg Phase-1 between Nagpur and Shirdi which was all set to be open for traffic from 1 May 2021 been postponed amid spike in COVID-19 cases across the state. 
 
Now as per the revised deadline, Phase-1 stretch will open in September and October 2021, only if the situation improves. 
 
The productivity of the workers' on the project site has drastically reduced due to the COVID-19 condition. The progress of construction work is slow compared to pre-COVID level. Also, due to the lockdown, the contractors are finding it difficult to procure raw material. 
 
Considering the alarming COVID-19 situation in the state, the government is engaged in providing medical facilities. Also, many government agencies have been roped in to set up COVID-19 care centres.
 
As per the initial plans, after Phase-1 opening in May 2021, Phase-2 stretch between Shirdi and Igatpuri comprising 103 km was supposed to be open for the public in December 2021. The remaining stretch of 78 km between Igatpuri and Wadpe near Mumbai was to be commissioned on 1 May 2022. However, due to the COVID-19 induced lockdown all phase deadlines have been postponed. 
 
Of the 701 km long Samruddhi Mahamarg project reportedly till 31 March 2021, around 52.6 percent of financial expenditure progress and 55 percent of the civil progress was recorded. 
 
The expressway passing through 10 districts, 26 talukas and 392 villages, once ready, will cut down travel time between Nagpur and Mumbai from to eight hours from the existing 16 hours.