Illustrative image – not actual.The Southern Railways' (SR) Salem-Karur new broad gauge line works in Tamil Nadu is unlikely to be completed by May 2011.
The project has been delayed owing to lack of financial support, pending land acquisition problems and resultant sluggishness in executing groundwork. The cost of the project has seen a few revisions and is now pegged at Rs 658.85 crore.
So far, a sum of Rs 250 crore has been spent while another Rs 70 crore has been spent from out of the funds made available in 2008-09. During 2009-10, a sum of Rs 56 crore has been spent from out of the budgetary grant of Rs 65.99 crore.
The total length of the project is 85.15 km. So far, 102 of the 131 minor bridges have been completed. Work on only 12 of the 45 rail over bridges (ROB) have been over while 16 rail under bridges of the total 21 have been completed. Besides them, 12 level crossings and eight stations are coming up under the project.
However, shifting of High Tension and Low Tension power line crossings remain to be completed at 20 locations. Construction of one ROB between Salem and Namakkal on the NH 7 has got stuck due to lack of proper traffic management by the NHAI while an estimated 30,000 cubic mtrs of earth work has not been taken up owing to delay in land acquisition near Rasipuram in Namakkal district.
Pending land acquisition problems have affected work on at least six ROBs - at Parapatti in Salem, Rasipuram, Namakkal, Vagurampati, Parali road, Kumarapalayam and near the Vangal station location.