Illustrative image – not actual.Salem City Municipal Corporation has stalled the Salem water pipeline project in Tamil Nadu due to delay in approval.
The Corporation has stalled the project as National Highways Authority of India (NHAI) is delaying permission. The project involves the laying of pipelines across the Salem-Bangalore National Highway, near Reddipatti Junction for Mettur.
The corporation's engineers studied the possibility of laying pipelines under the bridge near Karuppur, but it was found to be technically unfeasible.
The project comprises two stages with five packages under Stage-I and four packages under Stage-II. Work order for Stage-I was issued on August 27, 2010 and was scheduled to be completed by August 30, 2012.
Under package-V of the scheme, work is to lay pipelines for 11.90 km from Omalur - Tharamangalam Main Road to Mamangam and across the NH at Reddipatti Junction.