Illustrative image – not actual.Work on Public Works Department, Goa's 25 km long parallel pipeline from Salaulim to Margao is nearing completion. The last phase of the work, involving a length of 13 km and costing around Rs.36 crore, is almost complete and only about 1.7 km remain to be covered, which is expected to be completed by October 2008. The parallel pipeline will most likely be commissioned in December 2008.
The contractors were supposed to complete the project by March 2007. But delay in the work was partly because of delay in manufacture of specialised pipes and partly because of releasing payments to the contractors.
The parallel pipeline of mild steel (MS) pipes has been laid to overcome the perennial problem of the rupturing of the existing pre-stressed concrete (PSC) pipes and the accompanying water disruptions that have long bedeviled South Goa water consumers.
Once commissioned, the project will bring relief to the five lakh water consumers in the four talukas of South Goa.