The Sajjan Jindal group (formerly referred to as the OP Jindal group) has outlined a Rs.2,000 crore expansion project for its two companies -- Jindal Iron & Steel Co and Jindal Vijaynagar Steel Ltd. There is also move to merge the two companies.

The hot rolled capacity of JVSL will the ramped up to 4 million tpa from the present 2.5 million tpa. Jisco's cold rolling mill will be expanded to 1 million tpa from the existing 0.8 million tpa. The company's galvanizing capacity will also be stepped up to 9 lakh tpa.

To support the increase in steel capacity, a 200 MW gas-based power plant is being planned apart from ensuring coal supplies through equity participation in Australian coal mines.

The HR coil expansion will cost Rs.1,100 crore and will be completed by March 2006, while the CR mill and galvanizing plant project will be completed by March 2005.

It may be mentioned that JVSL and Jindal Strips have also been merged.