SAIL's Durgapur plant to invest Rs.3,000 croreIllustrative image – not actual.

Steel Authority of India has outlined a Rs.3,000 crore investment plan for capacity expansion at the Durgapur Steel Plant in West Bengal. The overall objective would be to increase crude steel capacity expansion from the current 1.8 million tpa to 3 million tpa, by 2012. 

The investment plan includes a bloom caster costing Rs.270 crore that would be commissioned by December 2005. The company would also re-activate its fourth blast furnace by March 2007.

DSP's plan is part of SAIL's overall plan of increasing steel capacity to 20 million tpa by 2012 across its four integrated steel plants at Durgapur, Bokaro, Bhilai and Rourkela. Incidentally, the National Steel Policy has envisioned India's steel capacity to reach 60 million tpa by 2012 from the current 35 million tpa. By 2020, India's vision is to attain capacity of 100 million tpa.