SAIL to commence Tasra project work with LancoIllustrative image – not actual.
Steel Authority of India (SAIL) is planning to commence work on the Tasra coking coal project with Lanco Infratech.

The work is scheduled to formally begin soon and a ceremonial unveiling is scheduled for 17 September 2017. The Tasra coal projetc is about 25 km from Dhanbad in Jharkhand.

The project will be developed by Lanco Infratech, with whom SAIL had signed an agreement in September 2013 to develop the project at a cost of Rs 400 crore in a period of two years.

The project’s cost has increased 10 fold to the present Rs 4,000 crore. The project now includes a 300 MW power plant.

The investment will be made by Lanco Infratech and reimbursed by SAIL.

The first year’s fund requirement for the project has been pegged at Rs 561 crore. The Tasra opencast mine is capable of yielding three lakh tonne of prime coking coal in the development stage, in the first year of production (the project is expected to begin in the second quarter of 2017-18) and 40 lakh tonne of coal by the fifth year, from which 20 lakh tonne of coking coal could be produced after washing. Tasra is about 25 km from Dhanbad in Jharkhand.