SAIL, RINL, NMDC plan Rs 12,889 cr capex in FY16Illustrative image – not actual.
Three major steel PSUs -- SAIL, RINL and NMDC - have proposed a marginal 1.4 per cent cut in their capital expenditure of Rs 12,889 crore, in the next fiscal towards modernisation and expansion plans.

 

According to the Union Budget document, Steel Authority of India (SAIL) proposes to spend Rs 7,500 crore, while Rashtriya Ispat Nigam (RINL) proposes to spend Rs 1,801 crore, and NMDC has earmarked Rs 3,588 crore for capital expenditure in 2015-16.

 

Though the three firms, under administrative control of the Steel Ministry, had proposed to spend Rs 15,393 crore in 2014-15, they may spend Rs 13,077 crore, as per the revised estimate, in the current fiscal.

 

SAIL plans to invest its Rs 7,500 crore capex earmarked for the next fiscal, in Bhilai, for a project worth Rs 2,586 crore; Rs 1,250 crore in Rourkela; Rs 1,100 crore in IISCO, Burnpur; Rs 940 crore in Bokaro; and Rs 730 crore in Durgapur.

 

Out of the Rs 1,402 crore capex for the next fiscal, RINL proposes to spend it on capital modernisation and expansion of its line plant in Vizag to 6.3 million tonne per annum from its present three million tonne per annum.

 

State-run iron ore miner NMDC, which is building a three million tonne per annum steel plant at Nagarnar, in Chhattisgarh, plans to spend the major portion of the plan outlay on the greenfield unit.

 

More project Info: 
Finished Steel (Visakhapatnam) Project - Expansion

Integrated Steel (Bhilai) Project - Expansion

Integrated Steel (Nagarnar) Project