Illustrative image – not actual.SAIL Launches Seven year 25K- crore Capacity Expansion Plan with Annual Outlay of Rs 4000 cr
SAIL today announced that will expand its production capacity in next seven years with total investment of Rs 25,000cr to increase its capacity to 20 million tonnes. SAIL will spend Rs 4000cr annually to achieve this target.
The proposed annual outlay of Rs 4000cr is 60% higher than SAIL’ s annual capital expenditure of Rs 2,500 crore, which was undertaken during mid 1990s.
SAIL has divided its expansion plan into two stages, in first stage, SAIL will be spending Rs 4,300 crore on priority schemes to be completed by 2006-07 and the remaining amount will be invested in the second stage between 2006-07 and 2011-12.
The company will fund its expansion expenditure through internal accruals and the rest by market borrowings.
The areas identified for investment plan are related to the development of iron ore mines, rebuilding coke oven batteries at the Bokaro and Durgapur steel plants. Additional blast furnace wiil be installed at Rourkela plant and new finishing mills.