SAIL board approves major expansion for Bokaro Steel PlantIllustrative image – not actual.

The board of Steel Authority of India has approved in principle a Rs.7,800 crore expansion project aiming to add 3 million tpa of steel capacity for its Bokaro Steel Plant in Jharkhand.

The project envisages increasing steel capacity from the present four million tpa to seven million tpa, by 2011-12, entailing an investment of around Rs.7,800 crore.

BSP has also planned to set up a 1.8 lakh tpa sponge iron plant with a view to overcome shortages of imported coke. A 1,250 tpd oxygen plant is also proposed to be set up by 2006-07. Another plant with the same capacity is likely to come up by 2011-12.

The integrated steel unit of SAIL is in the midst of implementing the following projects, all of which are in the tendering stage:

  • Modernisation of cold rolling mill (Rs.218 crore)
  • Rebuilding of coke oven battery No.5 (Rs.165 crore)
  • Slag granulation in blast furnace No.4 (Rs.33 crore)

In another development, BSP has planned to enter into a 50:50 joint venture with public sector Cement Corporation of India to set up a greenfield 1 million tpa cement plant. An agreement to this effect is likely to be finalized by August 2004.