Sahasra Semiconductors’ manufacturing plant project in Bhiwadi progressing wellIllustrative image – not actual.
Sahasra Semiconductors is setting up an Integrated Circuit Packaging Plant for memory at Bhiwadi in Alwar district of Rajasthan under PLI Scheme. 
 
The unit will have a capacity of 40 million numbers per year. It will also manufacture solid state drives for laptops and notebooks. 
 
In 2020, the Ministry of Electronics and IT accorded its approval under Production Linked Incentive Scheme (PLI Scheme) to the project. 
 
As per the update available with Projects Today, project execution work began at the end of 2020 and as of October 2022, around 80 per cent work on the project has been completed. 
 
The work on the unit is expected to be completed by the end of 2022.