Sadbhav Infrastructure Project’s wholly-owned subsidiary, Shreenathji-Udaipur Tollway (SUTPL) has received provisional completion certificate for Gomati Chauraha - Udaipur Section of NH-8 on 04 December 2015 and accordingly toll collection has been started on the project from 06 December 2015.
The project of four laning of Gomati Chauraha - Udaipur Section of NH-8 in the state of Rajasthan on DBFOT (Toll) basis was awarded by National Highways Authority of India (NHAI). The concession period was 27 Years (including Construction Period of 30 months) and appointed date was 18 April 2013 and concession period shall end on 17 April 2040. The total cost of project was Rs 1,151.5 crore out of which equity and sub-debt from sponsor shall be Rs 311.5 crore. The balance fund of Rs 840.0 crore has been provided by the Lenders which is to be repaid up to March 2031. The premium payment to NHAI is Rs 21.60 crore per annum (which shall increase by 5 per cent per annum).