Sadbhav Engineering (SEL) - S P Singla Constructions (SPSCPL) joint venture (JV) has been declared as the lowest (L1) bidder by the Gujarat Metro Rail Corporation (GMRC) for the Metro rail project.
The scope of work includes construction of 11.6 km elevated viaduct from Kadarsha Ni Nal to Dream City dead-end, including a ramp for depot entry near Dream City and 10 stations (exel E&M, architectural finishing and roofing) for Surat Metro Rail Phase-1, Package-CS1.
The bid project cost is Rs 805.15 crore with completion period of 30 months.
SEL holds a share of 74 percent in the SEL-SPSCPL JV, while SPSCPL holds 26 percent.