Rail Vikas Nigam (RVNL) has received a letter of acceptance (LoA) from Mumbai Metropolitan Region Development Authority (MMRDA) for the electrification package of Mumbai Metro Line-2B.
The scope of work includes the manufacture, supply, installation, testing and commissioning of two 110 kV receiving substation including 110 kV, 33 kV & 25 kV cabling work, complete 25 kV overhead catenary system along with switching station, 33 kV auxiliary power distribution system including 33/0.415 kV auxiliary sub-station (ASS) and complete SCADA system. The work will cover the main line and depot of Line-2B.
The project amounting to Rs 300.11 crore, is to be executed in a 36 month-timeline.
RVNL had participated in consortium with SIEMENS India, with SIEMENS as the lead partner with 60 percent share, RVNL as consortium partner with 40 percent share.