Illustrative image – not actual.The complex spread over 16 acre of land comprises 12 towers which are of G+35, G+30, G+28 floors with four flats each and modern amenities. Kapadia and Agar Associates is the architect for the project.
In February 2019, the State Level Environment Impact Assessment Authority (SEIAA) accorded environmental clearance (EC) for the project.
As per the latest information available with Projects Today, work on total nine towers is underway with completion schedule for tower one to seven by December 2019 and for tower eight and nine by December 2020. The work on tower 10, 11, 12 is yet to commence.