Illustrative image – not actual.The project comprises five towers of Phase-I and three towers of Phase-II, with a total 1,945 flats backed by modern amenities. In January 2017, KKR India Financial Services and KKR India Asset Finance invested Rs 315 crore for development of the project.
In February 2019, the State Level Environment Impact Assessment Authority (SEIAA) accorded environmental clearance (EC) for the project.
As per the latest development available with Projects Today, work on 25th floor of towers A, B and C for Phase-I is underway. On towers D and E, work on 35th floor is underway with completion scheduled for December 2022. Phase-II of the project is yet to be launched.