Illustrative image – not actual.Rajasthan State Power Corporation (RSPCL) plans to invite pre-qualification bids for the 140 MW integrated solar combined cylce (ISCC) power project coming up at Mathania, 30 kms from Jodhpur, in Rajasthan. In this connection, RSPCL would be organizing a two-day workshop and conference towards the end of October 2000.
The ISCC power project is
estimated to cost Rs.850-Rs.900 crore, financed by various Indian and foreign
sources. The state government plans to fund the project to the extent of Rs.50
crore through equity participation besides providing land for the project.
The Union government has decided
to sanction a grant of US $15 million (approx Rs.68 crore), while a German
development agency, KFW has agreed to a DM 250 million (approx Rs.525 crore) loan
to implement the project. Global Environmental Facility has decided to grant
$45 million (approx Rs.202 crore) to meet the incremental cost of the project,
which would use solar thermal power generation technology.
The ISCC project is expected to
use naphtha/gas fired gas turbines and steam turbines of 70 MW each. The steam
turbines would receive steam from the waste heat recovery boilers and solar
field of approximately 2,20,000 parabolic square metres, through collectors.
The project is expected to become
operational by 2003.