Rs 822-cr Jalasiri Water Supply Project in Mangaluru achieves 63 percent physical progressIllustrative image – not actual.

More than six years after the Karnataka state government launched the Rs 821.97 crore Jalasiri project to improve drinking water supply infrastructure in Mangaluru, the project has made significant progress.

According to the Karnataka Urban Infrastructure Development and Finance Corporation (KUIDFC), which is managing the project for Mangaluru City Corporation (MCC), physical progress stands at 63 percent and financial progress at 59.61 percent. The project involves the laying of a 52.57 km-long clear water transmission line, with 44.64 km already completed, and the installation of 1,155.36 km of water distribution pipelines, with 868.84 km laid so far. The project aims to provide water connections to 96,300 households, of which 37,025 have been completed. Regarding overhead tanks (OHTs), three out of 19 have been commissioned, civil works of 14 OHTs have been completed and civil works for one of the overhead tanks (OHT) are ongoing.

The construction of ground-level service reservoirs (GLSRs) and pump houses is progressing. The total project cost includes Rs 617.22 crore for the infrastructure and Rs 204.75 crore for maintenance over eight years. The project contract was awarded to SUEZ Projects - DRS Infratech (JV) in 2019.

← All latest storiesBack to top →