Illustrative image – not actual.Railways is set to replace the old mechanical interlocking system with the advanced route relay interlocking (RRI) system at the Danapur station. The station falls under the jurisdiction of the East Central Railway.
The project will be undertaken at a cost of Rs 50 crore to streamline traffic rush on the Pt Deendayal Upadhyay-Patna-Jhajha mainline section.
Danapur is an important station, which is now directly linked with the Pataliputra Junction.
The RRI work at the station has begun and will be completed in four phases by June 2019. Accordingly, the railways has, diverted at least 66 passenger trains to other routes and cancelled the remaining. Of the 89 stations located under the Danapur division, 80 are being linked to panel interlocking system to step up the safety measures on tracks.
The project will be undertaken at a cost of Rs 50 crore to streamline traffic rush on the Pt Deendayal Upadhyay-Patna-Jhajha mainline section.
Danapur is an important station, which is now directly linked with the Pataliputra Junction.
The RRI work at the station has begun and will be completed in four phases by June 2019. Accordingly, the railways has, diverted at least 66 passenger trains to other routes and cancelled the remaining. Of the 89 stations located under the Danapur division, 80 are being linked to panel interlocking system to step up the safety measures on tracks.