Illustrative image – not actual.Reliance Petroleum (RPL) is expected to complete its Jamnagar refinery ahead of its initial schedule of December 2008. The plant has an annual capacity of 27 million tpa.
Currently around 94 per cent of the work has already been completed which includes EPC activities. Meanwhile the construction activities are progressing rapidly to meet pre-commissioning requirements. By March 2008, RPL is said to have installed all major equipment, nearly completed equipment and bulk material deliveries and completion of civil construction.
Also See:
Jamnagar Petroleum Refinery Project: Status Report (17-Apr-08)
Related Links:
Project details