RPL to commission Sasan UMPP by 2013Illustrative image – not actual.

Reliance Power (RPL) is likely to commission the country's first ultra-mega power project - 4,000 MW Sasan Ultra Mega Power Project - by three years. From the earlier commissioning date of April 2016, Reliance Power has confirmed the advancement of the UMPP to March 2013.

Unit Capacity (MW) Commissioning Date (as per PPA) Commissioning Date (Advanced) Schedule advanced by
Unit 1 660 May 2013 Dec 2011 16 months
Unit 2 1,320 Dec 2013 Mar 2012 20 months
Unit 3 1,980 Jul 2014 Jun 2012 24 months
Unit 4 2,640 Feb 2015 Sep 2012 28 months
Unit 5 3,300 Sep 2015 Sep 2012 32 months
Unit 6 3,960 Apr 2016 Mar 2013 36 months

RPL has also committed to contribute 1,320 MW from Sasan to the 11th Plan capacity addition programme of the government. This is being done by advancing the commissioning of two units of Sasan of 660 MW each to March 2012, from the earlier plan of December 2013. The ministry of power has already instructed Power Grid Corporation of India to make necessary arrangements for timely evacuation of power from Sasan.

RPL has already awarded the Rs.14,000 crore EPC work for Sasan project to its group company Reliance Infrastructure, which has further placed the order for procuring boilers, turbine and generators (contract of Rs.10,000 crore) on Shanghai Electric Corporation of China.