RPL to commence production at its Jamnagar refineryIllustrative image – not actual.

Reliance Petroleum Ltd's (RPL) 5,80,000 bpd refinery at Jamnagar in Gujarat is likely to be fully functional by March 2009. However, RPL will begin producing some products by January 2009.

The company is likely to begin trial runs at the refinery being set up in a SEZ, adjacent to its parent firm's existing 6,60,000 bpd refinery by end-December 2008. At present, pre-commissioning activities at the unit are underway and checks were being carried out. The crude distillation unit may be ready to receive crude oil by end-December 2008.

Also See:

RIL to begin test runs at Jamnagar refinery(04-Oct-08)

← All latest storiesBack to top →