Illustrative image – not actual.Reliance Power (RPower) has signed a supplementary PPA with fourteen buyers from seven states for its upcoming 4,000 MW Sasan Ultra Mega Power Project (UMPP) in Sidhi district of Madhya Pradesh.
In May 2008, Reliance Power had committed to the Union Ministry of Power and Central Electricity Authority (CEA) to advance the commissioning schedule of Sasan by three years at a review meeting on UMPPs. The project, with captive coal mines, was earlier scheduled to be commissioned between May 2013 and April 2016, according to the earlier PPA.
As per the new schedule, commissioning of its first unit will be advanced by 16 months to December 2011 as against May 2013. The second unit will come after three months in March 2012. In total, 1,320 MW will be commissioned in the 11th Five-Year Plan itself.
Financial closure for the project is expected by November 2008. Reliance Power has also submitted the development plan for the pit-head mines to the ministry of coal and is awaiting the final clearance. The company is developing the mines in a strategic partnership with North American Coal Corporation.
Also See:
SC gives environmental clearance to Sasan UMPP (06-Sep-08)
Related Links:
Project profile