Illustrative image – not actual.RPG Group is likely to raise debt worth Rs 1,700 crore for its 600 MW greenfield thermal power project in Haldia in West Bengal. The company is likely to achieve financial closure for its proposed project by end-December 2009.
Currently, the company is holding talks with domestic and international lenders and a final decision is expected to be taken once CESC finalises the local-to-imported coal ratio for the proposed project. CESC is likely to import 30 per cent of the requisite coal for the Haldia greenfield project, while a majority 70 per cent will be sourced from the Mahanadi coalfields in Orissa.
Besides, the company is likely to decide the final amount of foreign loan after awarding the near Rs 2,300 crore EPC contract. Bids for the Haldia Stage-I EPC works are likely to be opened by the end-August 2009. The companies like BHEL, two Chinese power equipment makers - Dong Fang and Sepco Electric - are known to have evinced interest in the Haldia project.
Moreover, RPG is likely to invest Rs 150 crore for setting up a 81km transmission link that will connect CESC's Haldia power station with PGCIL's substation in Subhash gram.
Related Links:
Project profile