Following
a sharp increase in naphtha prices, the RPG group has decided to reduce the
generating capacity of its Dholpur Power Project at Dholpur in Rajasthan from
702 MW to 250 MW. This has resulted in the project cost falling to Rs.2,040
crore from Rs.2,288 crore.
As
per the original plans of the company, the first phase of the project was to
use naphtha as the fuel. However, a sharp increase in naphtha prices has
resulted in the company switching to high speed diesel as the input. The
project would now be undertaken for a generation capacity of 250 MW and the
remaining 452 MW would be considered whenever LNG becomes available as fuel.
Presently,
LNG is not available at the project site and it would take another two years
until it does. Incidentally, the state government did not approve the use of
coal for this project due to the potential adverse effects on the Taj Mahal
monument in the vicinity.
The
revised project is proposal is under consideration of the state government of
Rajasthan and is expected to be cleared soon.
The
company has already made several changes to the project since it was first
announced - such as reduction in capacity from 770 MW to 702 MW and the replacement
of Simens by ABB Alsthom as the EPC contractor.