Rohtak-Panipat Tollway (RPTPL), a wholly-owned subsidiary of the Sadbhav Infrastructure Project (SPV) vide its letter dated 27 July 2021, has submitted notice of termination of project as per concession agreement dated 9 March 2010 with the National Highways Authority of India (NHAI) due to forceful suspension of toll collection/user fee because of the farmers' agitation/protest with effect from 25 December 2020.
The event of forceful suspension of toll collection/ user fee because of the farmers' protest amounted to a force majeure event as per the provisions of the concession agreement with NHAI.
NHAI had awarded the work of four-laning of Rohtak-Panipat Section of NH-71A from 0.00 km (63.00 km of NH-10) to 80.858 km (83.39 km of NH-1) in the state of Haryana under NHDP Phase-III on design, build, finance, operate and transfer (DBFOT) basis to Rohtak-Panipat Tollway vide concession agreement dated 9 March 2010.
RPTPL had received appointed date on 18 April 2011 from NHAI. The original concession period is 25 years from the appointed date. The total length of the project is 80.858 km. The company achieved CoD on 6 January 2014.