Illustrative image – not actual.Around 22 percent of the works are already done with a scheduled completion date of 2021-end. The RGM International Airport works entails expanding the international terminal building and aprons and installation of four new air bridges. A VVIP pavilion will also be constructed.
The project will also include upgrading the ground lighting system and communication systems, and along with this will be service equipment such as ambulances, universal towing vehicles, airside buses and firefighting vehicles.
The works are being undertaken by Chinese construction company China Jiangsu International which also undertook expansion works for the Victoria Falls International Airport.
The funding for the RGM International Airport expansion works has been through a concessionary loan from the China Exim Bank that was availed after a state visit to Beijing by President Mnangagwa in 2018.
The project will be completed in a period of 36 months. It is expected that once complete the airport will be able to handle six million passengers annually.