Illustrative image – not actual.Ministry of Road Transport & Highways has invited bids for four laning of highways, which are not a part of National Highway Development Programme (NHDP).
The Ministry plans to undertake four laning about 10,000 km in the next 4-5 years. However this year it plans to carry out four laning of 3,000 km on build, operate and transfer (BOT) basis.
The Ministry would set up a panel of entrepreneurs for implementing non-NHDP project. The panel would comprise of the following categories:
|
Category |
Project Cost (Rs.crore) |
|
P150 |
Up to 150 |
|
P200 |
150 to 200 |
|
P250 |
200 to 250 |
|
P300 |
250 to 300 |
|
P400 |
300 to 400 |
|
P500 |
Up to 500 |
The scope of the project includes designing, engineering, financing, procuring, construction, operation and maintenance of the awarded section.
The last date for submitting request for empanelment is 18 April 2003.