River restoration work commencesIllustrative image – not actual.

The channelisation work for the river restoration and navigation project from Sangam bridge to Bund Garden in Pune in Maharashtra has commenced.

The river restoration project is to be implemented at a cost of Rs 600 crore. It envisages improving the condition of the Mula-Mutha river on a 16-km stretch from Rajaram bridge to Kharadi. The 46 nullahs or tributaries draining into the river will also be cleaned as part of the project. Once the channelisation is completed, beautification, desiltation and installation of sewage pipelines are to be taken up.

Of the total cost, Rs 67 crore for the work being carried out at present is covered under the JNNURM. This work is slated to be completed before June 2011. The remaining work is to be funded by the Asian Development Bank and private companies, among others.

While the Mahratta Chamber of Commerce, Industries and Agriculture is the promoter of the project. Naik Environment Research Institute (NERIL) is the consultants for the project. The DPR of the river restoration and navigation project has been completed by Pune Municipal Corporation, along with NERIL.

As per the DPR, 10-12 sewage treatment plants are to be set up along the river, Malhotra said. Besides, plans are in the pipeline for a nirmalaya kund, chowpatti food plaza, kite flying ground, bird watching centre, crematorium, entry-and-exit points, boat club, fuel station and recreation area, among others.

Apart from Sangam bridge, contractor for the work on Mhatre bridge to Sangam bridge has been finalised and work is likely to begin soon.