Illustrative image – not actual.Rio Tinto, Australia, has reportedly established a diamond sample processing plant at Bunder in Chhattarpur district of Madhya Pradesh.
The company is likely to invest Rs 2,200 crore in diamond exploration in India. It has already invested Rs 33 crore in the Bunder sample processing plant. So far, it has discovered eight lamporite formations and is upbeat on further explorations.
The Bunder plant is likely to sample 10 tonne per hour and it required less water than the conventional sample processing. The sample processing results are expected to come up by December 2009. The next phase of evaluation of the Bunder project is likely to involve engineering studies and the social and environmental impacts of a diamond mine. These studies are expected to take two to three years to complete.