Illustrative image – not actual.The Union government has completed the initial assessment of Rashtriya Ispat Nigam's detailed project report, it is learnt.
The final specifications are currently under preparation and the company has sought environment clearances.
The project costing around Rs.8,250 crore involves expansion of steel capacity from 3.5 million tpa to 7 million tpa is scheduled to be completed by March 2008.
Around Rs.5,500 crore will be sourced from internal accruals and the rest through borrowings. The debt component would include both Indian rupee borrowings and external commercial borrowings. The company will also consider suppliers' credit in the range of Rs.1,500 crore to Rs.2,000 crore on equipment.
In another development, RINL (the corporate avatar of Vizag Steel Plant) is considering setting up joint ventures for sourcing coal. The company does not have its own coal mines and is hence dependent on purchases. The steel major is reportedly evaluating possibilities of setting up joint ventures in China or Australia.
Also See: