Rashtriya Ispat Nigam has completed Phase-I of its expansion plans at Vizag Steel Plant. Following this, the steel manufacturing capacity of the company has increased from 3.6 million tonne per annum (tpa) to 6.3 million tpa.

 

Prime Minister, Narendra Modi, is expected to inaugurate the expanded facilities in the first week of July 2015.

 

The expanded plant, executed at a cost of Rs 12,300 crore, will commence commercial production in July 2015.

 

Presently, a trial run is on and production is expected to be stabilized by end July. In the second phase, the company intends to increase the steel manufacturing capacity to 10 million tpa.

 