Illustrative image – not actual.Rashtriya Ispat Nigam (also known as Visakhapatnam Steel Plant) has planned to invest Rs.3,000 crore in expanding its capacity from the current 3.5 million tpa to 5 million tpa, by 2008.
Around Rs.2,400 crore would come from internal accruals while BOT operators (for proposed oxygen plants) would fund the remaining Rs.600 crore.
RINL would further expand its capacity to 10 million tpa by 2018 involving an outlay (current prices) of Rs.17,000 crore. The interim target is to reach 6.8 million tpa by 2012.
The feasibility study of the expansion project is to be completed by end-July 2004 after which the proposal would be forwarded for government approval.
The company is also scouting for technology partners from Italy, Austria and Germany. RINL is also aiming at changing its product mix so that speciality steels would account for 50 per cent of total output, as against 25 per cent now.