Illustrative image – not actual.Rashtriya Ispat Nigam (RINL) on 6 August 2012 commissioned the high capacity waste gas fans of the new sinter plant of 3.6 million tpa capacity in Andhra Pradesh.
The commissioning of these fans is a major step towards readiness of new sinter plant as it is a very critical activity. This will facilitate the integrated cold trails of the new sinter machine to be commissioned shortly. With this, a major milestone was achieved for operationalisation of new sinter plant.