Illustrative image – not actual.
Reliance Infrastructure (RInfra) has won EPC orders for Rs 3,675 crore from NLC India (NLC) for setting up two nos. of lignite-based CFBC thermal power projects of 250 MW capacity each, in Barsingsar and Bithnok, in Bikaner district, Rajasthan.
The contract entails complete engineering, procurement and construction (EPC) on a turnkey basis, of two nos. of 1x250 MW power plant, based on Circulating Fluidized Bed Combustion (CFBC) technology.
The project is to be commissioned in 40 months, and will include boiler, turbine & generator (BTG) and balance of plant (BoP). RInfra bid was the lowest amongst the shortlisted bidders.
Bithnok thermal power project (250 MW) with the linked lignite mine of 2.25 million tpa capacity at Bithnok, is being set up by NLC, for which a power purchase agreement has been signed with Rajasthan DISCOMs.
Barsingsar thermal power station extension (250 MW) with linked Hadla lignite mine of 1.9 million tpa is an extension of the existing power plant at Barsingsar. Both the projects are set for commissioning in 2020.