Illustrative image – not actual.Reliance Industries (RIL) is all set to begin test run of its new oil refinery at Jamnagar in Gujarat and is scheduled for completion by December 2008.
The refinery, set up at a cost of around $6 billion, will be commissioned in phases. The refinery is coming up in a SEZ adjacent to RIL's existing 6.6 lakh bpd refinery at Jamnagar. The refinery, in which Chevron Corporation holds a 5 per cent stake, is equipped to process cheap, low-grade crude into gasoline and diesel that meet strict Western standards. Initially, the refinery will produce Euro-IV grade petrol and diesel and later upgrade to Euro-V. Fuel from the refinery will be mostly exported to the U.S. and Europe. The company is also looking at other markets for exports.
Also See:
RPL's Jamnagar refinery to complete ahead of schedule (23-Jul-08)