Reliance Industries (RIL) is likely to drill one gas well and convert two sick oil wells into gas wells on the MA oilfield in the KG-D6 block as part of its attempts to enhance gas production.
RIL has so far drilled six wells on the MA oilfield, the only oil discovery among the 19 oil and gas finds the company had made in the eastern offshore KG-DWN-98/3 or KG-D6 block. However, two out of the six wells had to be closed due to high water and sand ingress leading to drop in output.
Together with 21.93 mmscmd of output from Dhirubhai-1 and 3 or D1&D3 gas field, the KG-D6 block currently a little less than 27.5 mmscmd of gas. As per RIL’s revised field development plan, it has scaled down the investment required for developing the MA oilfield by $276 million to $1.96 billion.
Meanwhile, RIL-BP will submit a revised development plan for D1&D3 gas fields, the main producing area in KG-D6, by October 2012.