Illustrative image – not actual.Reliance Industries (RIL) may have to stop natural gas supplies to steel plants, petrochemical units and refineries if it is to implement a Union Ministry of Petroleum's directive.
In the event of falling KG-D6 output by 20 per cent, the ministry order has asked RIL to first supply fuel from its eastern offshore KG-D6 fields to priority sectors like fertiliser and power. RIL produced 47.5 mmscmd of gas from KG-D6 fields in the week ended 26 March 2011, down from 61.5 mmscmd output achieved a year ago.
So far, RIL has signed up customers for 60.76 mmscmd of gas while production is less than 48 mmscmd. The government had accorded highest priority to fertiliser plants followed by LPG extraction units, power plants and city gas distribution projects in allocating KG-D6 gas.
The priority sector allocation totals 47.59 mmscmd, leaving almost nothing for steel plants, refineries and petrochemical units, if the ministry order is implemented.