Illustrative image – not actual.The Managing Committee, constituted under the Production Sharing Contract, consisting of contractors and government of India nominees has approved Reliance Industries' Field Development Plan (FDP) of MA field (Dhirubhai-26), within the contract area of KG-DWN-98/3 (KG-D6), located in the Krishna Godavari basin off the east coast of Andhra Pradesh
The field is estimated to produce a peak oil production of 40,000 bopd and an estimated gas of 240-350 mmscfd. The production is likely to commence by mid 2008 and the MA oil field development plan is in addition to the development plan for gas field D1-D3 within the same block.
The field was discovered by RIL in 2006. RIL acquired this block, KG-DWN-98/3 under NELP-I and holds a participating interest of 90 per cent and Niko (NECO) Ltd holds the remaining 10 per cent participating interest.