RIL evaluate development plans for D6 satellite fieldsIllustrative image – not actual.

Reliance Industries is aiming to produce an additional 40 mmscmd from the D6 Block in offshore Krishna-Godavari Basin by developing satellite fields in the area.

RIL has made eight gas discoveries in the satellite fields and has already submitted the development plan for these fields. The Director General of Hydrocarbons is currently evaluating the development plan of the satellite fields. The discoveries are adjacent to the Dhirubhai 1 and Dhirubhai 3 gas fields, which are currently under development and are expected to start production from the end of October 2008.

As per the development plan submitted by RIL, the satellite fields are estimated to hold around 3 tcf of gas and is likely to push up the total gas production from D6 by 30-40 mmscmd. The gas in the satellite fields in D6 Block is estimated to increase the reserves of D6 Block to around 17.5 tcf from the current 14.5 tcf.

Also See:

RIL appoints AGR Group as KG gas adviser (29-Aug-08)

← All latest storiesBack to top →