Illustrative image – not actual.Reliance Industries has successfully completed the drilling of wells KG-D6-AA1 and KG-D6-Q1 in the deepwater block KG-DWN-98/3 (KG-D6).
The well KG-D6-AA1 was located in the new 3D seismic area at a water depth of 1.858 metre and drilled to a depth of 2,862 metre. The well KG-D6-Q1 is located at a water depth of 1,832 metre and drilled to a depth of 2,945 metre. The Q1 well is approximately 15 km southwest of AA-1 and 8 km northwest of the P1 natural gas discovery. Both the wells have encountered pay zones in the distal part of the earlier established channel levee systems in the KG-D6 block.
Further, drilling of the well KG-D6-P2 is in progress. RIL's development of the gas discoveries Dhirubhai 1 and Dhirubhai 3 is on schedule for production and supply of gas by 2008. The pre-engineering survey for offshore installation has been completed.