RIL-BP to submit field development plan for KG-D6Illustrative image – not actual.

Reliance Industries (RIL) and partner BP Plc will submit to the Central Government an integrated development plan to produce natural gas from all the 18 discoveries in the KG-D6 block by October 2012.

The two partners proposed first gas from R-Series, the third-largest gas find in the eastern offshore KG-DWN-98/3 or KG-D6 block, by 2015 and production from satellite fields by 2016 subject to timely regulatory approvals. The development plan will help in cost savings of over $1 billion (approx Rs 5,000 crore) due to integration and optimisation. In addition, un-incurred Phase II cost of D1&D3 field development plan ($3.1 billion out of total cost of $8.8 billion) will not be required to be spent. Once the integrated plan is approved, RIL-BP will relinquish most of the 7,645 sq km KG-D6 block.