Rihand Unit IV to turn commercialIllustrative image – not actual.

NTPC will begin commercial power generation from its 500 MW Unit IV of the Rihand super thermal power project in Uttar Pradesh, from 1 April 2006.

The unit was synchronized to the northern grid in late-September 2005. The total capacity at the Rihand plant stands at 2,000 MW coming from four units of 500 MW each. Bharat Heavy Electricals was the EPC contractor for Unit IV, with an order value of Rs.2,079 crore.

The Rihand plant began operations in March 1988 when the first unit of 500 MW was commissioned. The second unit was commissioned in July 1989.  The expansion project of adding two more units of 500 MW was initiated in early 2000. The third unit of 500 MW was made operational in February 2005, eight months ahead of schedule.

It may also be mentioned that in late-March 2006, the NTPC board cleared an investment of Rs.2,448 crore in developing Stage III (500 MW) of the Korba super thermal power project in Chhattisgarh.

 