Rihand power project: Full commissioning in May 2005Illustrative image – not actual.

The second unit of 500 MW of NTPC's Rihand Super Thermal power project (Stage II) in Sonbhadra district of Uttar Pradesh is likely to be completed in May 2005, according to BHEL.

In early February 2005, BHEL commissioned the first unit of 500 MW taking the total capacity of the power plant to 1,500 MW. This unit will have a daily power generation of 120 lakh kwh.

BHEL had bagged the Rs.2,079 crore order for the main plant package for two units of 500 MW each.

The final capacity of the Rihand Power station  will be 2,000 MW comprising four units of 500 MW. The first two units were commissioned in March 1988 and July 1989, respectively.