RGPPL’s LNG unit plan hits hurdleIllustrative image – not actual.

Ratnagiri Gas and Power’s (RGPPL’s) efforts to build a breakwater facility and ramp up production at an LNG re-gasification unit have been stalled, with key promoter NTPC declining to pump in the required Rs 600 crore.

The project has a debt-to-equity ratio of 1:1. And while the consortium of banks will provide Rs 1,200 crore as debt, GAIL and NTPC will be required to contribute Rs 600 crore each as promoters’ equity.

RGPPL wants to construct a breakwater facility to facilitate ships to berth at its docks throughout the year. While it can receive around 10 ships at present, the breakwater facility will allow it to receive upto 80 ships in a year.