Illustrative image – not actual.Ratnagiri Gas & Power is likely to generate electricity using gas as a feedstock by mid-August 2007.
GAIL (India), an equal promoter in RGPPL, on 10 July 2007 transported gas to the plant through a new pipeline from Dahej in Gujarat. Despite the 577-km pipeline transporting the gas, the plant could not take gas supplies as RGPPL was not able to provide guarantees for fuel payment. The Dabhol power plant will receive gas at $5.84 per million British thermal units (mbtu).
Petronet LNG (PLL) has signed a gas sales agreement with GAIL, Indian Oil Corporation and Bharat Petroleum Corporation for offtake of the short-term LNG it is importing from RasGas of Qatar. After re-gassification, the gas is transported through GAIL's pipeline to the power project. GAIL is in talks with Sonatrach of Algeria for long-term contract of import of 2.5-5 million tpa of LNG from 2010 once Dabhol plant's LNG receipt facility is fully completed.
Also See:
Ratnagiri power project set to generate 1,400 MW (12-Jul-07)