Illustrative image – not actual.The Department of Power of West Bengal, the implementing agency of RGGVY intends to cover the 244 mouzas in Phase II which could not be covered in Phase I of the rural electrification programme.
The 244 mouzas could not be covered under mouza electrification programme in the Phase I due to disputes and litigation. In Phase II, the state power department plans to intensify the electricity distribution networks in 81,967 rural habitations in 33,000 mouzas in all the 18 districts in the state, to provide access to electricity to a further 52,89,607 rural households. The electrification work is expected to be completed in the next three years.
By March 2009, under RGGVY project, around 45 lakh rural households became metered consumers of West Bengal State Electricity Distribution Company. The total provisioned fund of Rs 3000 crore has been mobilised, work orders have also been issued.