Revised estimates approved for three thermal power projectsIllustrative image – not actual.
The Maharashtra cabinet has given its approval to the revised estimates for expansion of three thermal power plants located in Chandrapur, Koradi and Parli.

The total revised cost is Rs 23,112 crore, while the original cost, which was estimated along with the approval in 2008 and 2009 amounted to Rs 18,755 crore.

Of the Rs 3,305 crore capital investments required, the state government will provide Rs 820 crore, and Rs 2,485 crore will be raised through financial institutions.

Once completed, the power generation of the thermal power plant will be raised by 2,730 MW.

Permission was granted in 2008 to set up transmission to raise additional power generation to 500 MW at Chandrapur thermal power plant with an investment of Rs 5,500 crore. However, implementation of the project led to cost escalation due to increase in market prices of the material required and also due to inordinate delay in its execution The revised cost for the project is now Rs 7,004 crore.

There was a major delay from the contractors in the completion of Koradi thermal power plant’s expansion, leading to cost escalating to Rs 14,026 crore from the earlier Rs 11,880 crore.