REpower wins contract from C-PowerIllustrative image – not actual.

REpower Systems AG bagged a contract from C-Power, a Belgium based offshore project development company, for the delivery of 48 of the REpower 6M type wind energy turbines.

The turbines have a total rated power of approx 295 MW and are envisaged for Phases II and III of the Thornton Bank wind farm. The installation of 24 turbines for Phase II is planned for 2012, and a further 24 turbines are to be installed by mid-2013.

A consortium of seven commercial banks, together with the European Investment Bank is providing approx EUR 900 million (approx Rs 5,490 crore) for the project..

REpower’s scope of work includes production and delivery of the nacelles, towers, blades and hubs as well as pre-installation in the port of Oostende. Further, REpower is responsible for the installation, commissioning and the test run of the turbines.

Suzlon Energy has 90 per cent share holding in REpower.